Explore our Solution Library

Number of Views - 848 85

San Diego State University Operations And Supply Chain Management Assignment Help - Mean


Question - Mike Dreskin manages a large Los Angeles movie theater complex called Cinema I, II, III, and IV. Each of the four auditoriums plays a different film; the schedule is set so that starting times are staggered to avoid the large crowds that would occur if all four movies started at the same time. The theater has a single ticket booth and a cashier who can maintain an average service rate of 280 movie patrons per hour. Service times are assumed to follow an exponential distribution. Arrivals on a typically active day are Poisson distributed and average 210 per hour. To determine the efficiency of the current ticket operation, Mike wishes to examine several queue operating characteristics. (a) Find the average number of moviegoers waiti ...Read More

Solution Preview - No Solution Preview Available

Found What You Need?

Scroll down to find more if you need to find our more features