Western Governors University Operations And Supply Chain Management Assignment Help - Managerial Modeling


Question - 2s 6. Bismarck manufacturing intends to increase capacity through the addition of new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $65,000, and for proposal B, $34,000. The variable cost for A is $10, and for B, $14. The revenue generated by each unit is $18. a) What is the break-even point for each proposal? b)If the expected volume is 8,300 units, which alternative should be chosen?

Solution Preview - No Solution Preview Available