university of southern california Operations And Supply Chain Management Assignment Help - project manager

Question - Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on a project in which concrete pillars were being constructed however not all the data are available. She has been able to find out that the 10th pillar required 260 person-hours to construct, and that a 75% learning curve applied. She is interested in calculating the time required to construct the 15tand 20th pillars. Compute the values for her.