Question - task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: a 6.0 - b 7.2 - c 5.0 a d 6.0 b,c e 4.5 b,c f 7.7 d g 4.0 e,f a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project.